Start page > Construction
Danish
Construction


Week 41-44. Monday 5 October till Sunday 31 October.
The  new parking space has now been finalised along with the new acess road.


DanCopter DanCopter DanCopter





Week 38-40. Monday 14 September till Sunday 4 October.
We are almost ready to open the new parking space along with the new access road.


DanCopter DanCopter DanCopter





Week 35-37. Monday 24 August till Sunday 13 September.
Here is a look at hangar 3 and the parking space. Work is still being conducted in these areas. 


DanCopter DanCopter DanCopter





Week 29-34. Monday 13 July till Sunday 23 August.
During the summer the new office building has been completed. Friday 14 August we said goodbye to the containers which served as office as well as meeting facility and moved into the new offices. The third hangar and the parking space is expected to be completed within the next two months and with that the entire construction project has been completed.


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter





Week 25-28. Monday 15 June till Sunday 12 July.
The construction is really beginning to take shape and not much is lacking before we can pronounce the constuction for complete.


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter





Week 23-24.  Monday 1 June till Sunday 14 June.
The roof on hangar 3 is almost finish and the new administration building will soon have an interior as well as an exterior staircase. 


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter





Week 20-21-22.  Monday 11 May till Sunday 31 May.
The construction is proceeding according to plan. Soon hangar 3 will be appearing with a roof while the work on the new administration building continues on the first floor and with the painting of the ground floor.  


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter





Week 17-18-19.  Monday 20 April till Sunday 10 May.
On Thursday 30 April we held a topping-out ceremony for our new buildings; administration and hangar 3 respectively. All trusses on the administration building were, however, already in place but it was decided to combine the two ceremonies in one. Speeches were held by Jan Madsen (LM Huse) and Nils Skeby (DanCopter) and curious DanCopter employees inspected the new buildings. The pictures below show the new administration building from the inside as well as the increasing number of portable cabins in DanCopters parking area.


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter





Week 14-15-16.   Monday 30 March till Sunday 19 April.
The construction is proceeding according to plan. The fine air photos is captured by Thomas Vesth on 14 April.


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter





Week 13.  Monday 23 March till Sunday 29 March 2009.
The construction of the new administration building continues with the erection of first floor.


DanCopter DanCopter DanCopter





Week 12.  Monday 16 March till Sunday 22 March 2009.
After founding the base the construction of the new administration building commenced and so did the ditching for the new and third hangar.


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter





Week 11.  Monday 9 March till Sunday 15 March.
The previous weeks the constructors have been preparing the foundation for the new building and they are now getting ready to cast the foundation.


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter

DanCopter





Week 8.  Monday 16 February till Sunday 22 February.
This week the extension of our administration and hangar facilities at DanCopter´s base in Esbjerg commenced. First step was to move Operations and our meeting room into portable cabins placed outside the existing administration building. The vacated offices was following blocked and made ready for the removal of the end wall towards Esbjerg Airport. DanCopter´s entire parking space has been converted into storage of the portable cabins and construction site.


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter


DanCopter DanCopter DanCopter







 


Contact information for Blueway Offshore Norge